_____________________________________________________________________
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
____________
FORM 8-K
CURRENT REPORT
PURSUANT TO SECTION 13 OR 15
(d)
OF THE SECURITIES EXCHANGE ACT OF 1934
DATE OF EARLIEST EVENT REPORTED: JANUARY 9, 2008
ATWOOD OCEANICS, INC.
(Exact name of registrant as
specified in its charter)
COMMISSION FILE NUMBER 1-13167
TEXAS
(State or other jurisdiction of incorporation or organization)
Internal Revenue Service – Employer Identification No. 74-1611874
15835 Park Ten Place Drive, Houston, Texas, 77084
(281) 749-7800
____________
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2. below):
[ ] Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
[ ] Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
[ ] Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
[ ] Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
During the first
quarter of fiscal year 2008, the following unplanned zero rate days were
incurred:
ATWOOD HUNTER Three (3) zero rate days due to equipment related issues
ATWOOD EAGLE Five (5) zero rate days due to equipment related issues
SEAHAWK Sixteen (16) zero rate days due to equipment related issues
All of the
above unplanned zero rate days have
reduced revenue for the first quarter by approximately $3 million or $0.09 per
diluted share.
In addition to the above unplanned zero rate days,
the following planned zero rate days were incurred during the first quarter:
ATWOOD EAGLE Fourteen (14) zero rate days for regulatory inspections
RICHMOND Eighty-one (81) zero rate days due to being in a shipyard for its life enhancing upgrade
The
ATWOOD HUNTER entered into a shipyard in Malta on January 4, 2008 to undergo
certain equipment upgrades. The rig will be at zero rate during this shipyard
period which is expected to extend to January 25, 2008. Upon the completion of
these equipment upgrades, the rig will be relocated to Mauritania (estimated to
take twenty-one (21) days at a dayrate of $228,000) to commence working under the
suspended Woodside Energy Ltd (“Woodside”) contract at a dayrate of
$240,000. Woodside did not exercise its option to extend the contract beyond its
current expected termination in August 2008. Contract commitments beyond August
2008 are currently being pursued.
The ATWOOD SOUTHERN CROSS has completed its drilling
commitments in the Black Sea and is currently preparing to mobilize back to the
Mediterranean Sea (estimated to take around twenty (20) days at a dayrate of
$100,000). Upon arriving in the Mediterranean, the rig will drill one well for
Turkiye Petrollei A.O. (“TPAO”) which is estimated to take forty-five
(45) days to complete at a dayrate of $320,000. Upon completion of the drilling of
the TPAO well, the rig will be mobilized to Italy (estimated ten (10) days at a
dayrate of $365,000) to commence a drilling program for ENI Spa AGIP Exploration
& Production Division (“ENI”). The ENI commitment includes the
drilling of two (2) firm wells plus options for the drilling of two (2) more wells
all at a dayrate of $406,000. If all four (4) wells are drilled, this program could
extend to November 2008. The rig could incur four (4) to ten (10) zero rate days
between the completion of the TPAO well and commencement of the ENI drilling
program for some maintenance work.
Our new Jack-up drilling unit (the ATWOOD AURORA)
currently under construction in Brownsville, Texas is now scheduled for delivery in
November 2008. We are pursuing contract opportunities for the ATWOOD AURORA outside
of the United States. With an anticipated lengthy mobilization period, the drilling
unit will probably not commence earning revenues until January/February
2009.
The ATWOOD EAGLE’s remaining
drilling commitment with BHP Billiton Petroleum Pty (“BHPB”) is
expected to extend to the end of May 2008. The remaining wells drilled under this
contract will have a dayrate of approximately $170,000. Following completion of the
BHPB program, the rig will drill one (1) well for ENI (expected to take around
forty-five (45) days to complete) at a dayrate of $360,000 and then commence its
two (2) year commitment with Woodside Energy Ltd (“Woodside”) at a
dayrate of $405,000. Following completion of the Woodside drilling program
(estimated July 2010), Chevron Australia Pty. Ltd. (“Chevron”) has
committed to use the rig at a dayrate of approximately $430,000/$450,000 (subject
to adjustment for cost escalation) until our new semisubmersible drilling unit
being built in Singapore is ready to commence its drilling program commitment in
Australia with Chevron. Chevron has an option to continue to use the ATWOOD EAGLE
for a mutually agreed term after the new semisubmersible drilling unit arrives in
Australia.
The RICHMOND continues to undergo its life
enhancement upgrade which is now expected to be completed in mid-February 2008 at a
cost of approximately $17 million. Following the completion of this life enhancing
upgrade, the rig has contractual commitments with Helis Oil & Gas
(“Helis”) and Contango Operations, Inc. (“Contango”) both
of which have engaged Applied Drilling Technology Inc. (“ADTI”) to
manage the drilling operations. The Helis contractual commitment involves the
drilling of one (1) well at a dayrate of $80,000 for approximately the first thirty
(30) days and a dayrate of $65,000 for any additional time required to complete the
drilling program. The Contango contractual commitment involves the drilling of two
(2) firm wells plus an option to drill one (1) additional well at a dayrate of
$65,000 for all three (3) wells. We expect to drill the Helis commitment
immediately following the rig’s shipyard work; however, this commitment could
be deferred to a later date in 2008. If all four (4) wells are drilled, these
drilling commitments could extend to September 2008.
A copy of the press release reporting the new
contract commitments for the ATWOOD EAGLE and RICHMOND is filed with this Form 8-K
as Exhibit 99.1 and is incorporated herein by reference.
Statements contained in this report with respect to the future are forward-looking statements. These statements reflect management's reasonable judgment with respect to future events. Forward-looking statements involve risks and uncertainties. Actual results could differ materially from those anticipated as a result of various factors including; the Company's dependence on the oil and gas industry; the risks involved the construction of a rig; competition; operating risks; risks involved in foreign operations; risks associated with possible disruption in operations due to terrorism; risks associated with a possible disruption in operations due to a war with Iraq; and governmental regulations and environmental matters. A list of additional risk factors can be found in the Company's annual report on Form 10-K for the year ended September 30, 2007, filed with the Securities and Exchange Commission.
ITEM 9.01 EXHIBITS
EXHIBIT 99.1 Press Release dated January 9, 2008
EXHIBIT INDEX
EXHIBIT NO. DESCRIPTION
99.1 |
Press Release dated January 9, 2008 |
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
DATE:
January 9, 2008 |
ATWOOD
OCEANICS, INC. |
EXHIBIT EX. – 99.1
ATWOOD
ANNOUN
CES NEW COMMITMENTS
FOR
ATWOOD EAGLE AND RICHMOND
Houston, Texas
9 January 2008
FOR IMMEDIATE RELEASE
Atwood Oceanics, Inc. (Houston based
International Offshore Drilling Contractor – NYSE ATW) announced today
that the ATWOOD EAGLE’s
remaining drilling commitment with BHP Billiton Petroleum Pty (“BHPB”)
is expected to extend to the end of May 2008. The remaining wells drilled under
this contract will have a dayrate of approximately $170,000. Following completion
of the BHPB program, the rig will drill one (1) well for ENI (expected to take
around forty-five (45) days to complete) at a dayrate of $360,000 and then commence
its two (2) year commitment with Woodside Energy Ltd (“Woodside”) at a
dayrate of $405,000. Following completion of the Woodside drilling program
(estimated July 2010), Chevron Australia Pty. Ltd. (“Chevron”) has
committed to use the rig at a dayrate of approximately $430,000/$450,000 (subject
to adjustment for cost escalation) until our new semisubmersible drilling unit
being built in Singapore is ready to commence its drilling program commitment in
Australia with Chevron. Chevron has an option to continue to use the ATWOOD EAGLE
for a mutually agreed term after the new semisubmersible drilling unit arrives in
Australia.
The RICHMOND continues to undergo its life
enhancement upgrade which is now expected to be completed in mid-February 2008 at a
cost of approximately $17 million. Following the completion of this life enhancing
upgrade, the rig has contractual commitments with Helis Oil & Gas
(“Helis”) and Contango Operations, Inc. (“Contango”) both
of which have engaged Applied Drilling Technology Inc. (“ADTI”) to
manage the drilling operations. The Helis contractual commitment involves the
drilling of one (1) well at a dayrate of $80,000 for approximately the first thirty
(30) days and a dayrate of $65,000 for any additional time required to complete the
drilling program. The Contango contractual commitment involves the drilling of two
(2) firm wells plus an option to drill one (1) additional well at a dayrate of
$65,000 for all three (3) wells. We expect to drill the Helis commitment
immediately following the rig’s shipyard work; however, this commitment could
be deferred to a later date in 2008. If all four (4) wells are drilled, these
drilling commitments could extend to September 2008.
Statements contained in this report with respect to the future are forward-looking statements. These statements reflect management's reasonable judgment with respect to future events. Forward-looking statements involve risks and uncertainties. Actual results could differ materially from those anticipated as a result of various factors including; the Company's dependence on the oil and gas industry; the risks involved the construction of a rig; competition; operating risks; risks involved in foreign operations; risks associated with possible disruption in operations due to terrorism; risks associated with a possible disruption in operations due to a war with Iraq; and governmental regulations and environmental matters. A list of additional risk factors can be found in the Company's annual report on Form 10-K for the year ended September 30, 2007, filed with the Securities and Exchange Commission.
Contact:
Jim Holland
281-749-7804